- Nagpur 3rd/4th line -
🟩CR has completed 147.77 km multitracking (new line/doubling/3rd/4thline) in current FY from April 2023 till date 2023.
🟩3886.95 Crs planned by CR in this year for new lines/doubling/3rd/4th line/
🟩2983.47 Crs expenditure till date
🟩Wardha - Nagpur 3rd/4th line -
➡️Length - 78.70 km
➡️Length commissioned - 34.59 km
➡️Remaining - 44.11 km
➡️Overall Physical Progress - (3rd line-72%) (4th line-70%)
🪙 Cost - 1177.97 Cr
🪙 Expenditure till date - 1035.92 Cr
A) Completed 3rd/4th line section
🟩Khapri - Sindi - 34.59 km (43.95%)
B) Near Completion Section (27.14 kn (34.48%)
🟩Sindi - Seloo Road
🟩Khapri - Ajni
C) In Progress Section 16.97 km (21.56)
🟩Seloo Road - Wardha
🟩Ajni - Nagpur
➡️Land acquisition required - 38.858 Hectare
➡️Land acquisition completed - 38.818 Ha (99.50%)
➡️Land acquisition remained - 0.04 Ha
🟩Completed works details -
➡️Earthwork including blanketing - 21.40/32.63 Lcum(66%)
➡️Important Bridges - 2/2 (100%)
➡️Major Bridges - 10/12 (83%)
➡️Minor Bridges - 69/144 (48%)
➡️Station building - 2/7 ( 28%)
➡️Track linking - 69/157 km (44%)
➡️OHE (Overhead equipment) Foundation- 1010/4048 (25%)
➡️OHE Mast erections - 890/3680 (24%)
➡️OHE Wiring Track km- 45/184 (25%)
➡️Signalling Electronic Interlocking - 6/20 Stations (30%)
➡️Signalling Indoor and Outdoor works - 6/20 (30%)
🟩Completion of Wardha - Nagpur section 3th/4th lines will help to increase train mobility and will reduce congestion of section on busy Mumbai Howrah Route.