Connecting Sikkim with Rail Network!
Progress Report: Sivoke - Rangpo project till 31.07.22
14 Tunnels: 52.31% work completed (20.25 km of 38.71 km)
13 bridges: 33% work completed (Foundation & substructure in progress)
Earthwork progress:...