##Pics taken today 15th December morning after yesterday's successful CRS of BhagalpurJn to Lailakh Mamalka doubling (part of SBG Loop Doubling)
##Only 16 km lailakh Mamalka to Kahalgaon doubling left now in which 80% work has been completed and bridges are also completed.
##Interlocking to new track to BhagalpurJn is to be done after CRS report work on BhagalpurJn going on to lay tracks of sleepers and fixing them through support.
##Vikramshila...
more... standing at yard and BGP LTT superfast comming out of yard and changing tracks before being placed at platform no 1.
##Electrification progress: From JMP side all poles laid till BGP platforms, no poles in yards from mahesi(just before Nathnagar) all poles fixed but Hookes are not set everywhere and at BhagalpurJn all poles has not been interconnected.