For doubling updates using #PuneSolapurDoubling
Hotgi bypass line is in operation.
SUR Division planned to add two more lines between Solapur & Hotgi for frieght movement of Coal Trains for NTPC, but this line was occupied by illegale houses by locals. So CR dropped this plan.
Construction of Daund bypass line is in progress and expected to complete by March 2019....
more...
Daund ELS will take at least 2 years to complete.
Solapur - Osmanabad new line survey is submitted and sent to RB for final approval.
Solapur - Dhule 4 Lane highway is 90% completed.
When you visit Solapur next time, you will see complete makeover.