Ratan Ji,
Jab aadhi aduri information hoti hai tab aise hi comments aaten hain. Its Indian railways and all work are either depends on different departments or they need RB permission.
Again telling you the rest of the task pertains to ASH/Aishbagh - STP/Sitapur section :
1. Non-Interlocking would be done by last week or April;2018 or first week of may;2018 (Non-Interlocking : Creating...
more... signal point manually)
2. Mega block : In month of May;2018 mega block for connecting STP/Sitapur junction to rest of track will taken as it required RB permission
3. CRS : June or so CRS will be conducted
4. CRS finding : July;2018 onwards CRS finding and station work will continue
5. Commencement : Aug;2018 or so inagural train will start and post which regular DEMU run will start from ASH/Aishbagh - STP/Sitapur.
Humble request please don't spread rumors. Said sections GC already been delayed and next year we have election so before its too late NER want to open.