ECoR doubling and electrification targets for 2016-17
1. Tokopal-Bodearpur railway section (5.6 km long) of Jagdalpur-Kirandul doubling project will be completed by November this year
2. Sargipalli-Handapa section (14 km) of Sambalpur-Talcher doubling project will be completed by February next year.
3....
more... ECoR has set February date for Titlagarh-Kantabanji section (33.29 km) of Raipur-Titlagarh doubling project, Chudangarh-Bhubaneswar New railway section (7.3 km) of Rajathagarh-Barang doubling project and Mancheswar-Bhubaneswar New section (6.66 km) of of Khurda Road-Barang third line project.
4. Singapur Road-Lanjigarh Rd section (78 km) and Lanjigarh Road-Titlagarh Jn (47 km) of Vizianagaram-Titlagarh project will be completed by end of December this year and February next year respectively.
5. Lapang-Sambalpur section (32 km) of Jharsuguda-Sambalpur project will be ready by February next year.