– 45.33 Cr
🛑Overall Physical Progress – 40%
✳️Scope of work-
➡️Construction of 4 nos. stabling lines with secondary maintenance facilities.
➡️Construction of 1 pit line.
➡️Construction of Service buildings for Mechanical department.
➡️Construction of 2 new platforms with 2 new loop lines.
➡️Construction of cover over shed with coach watering facility.
➡️Construction of foot over bridge connecting existing platforms to proposed platforms.
✳️Completed work-
➡️Contracts for all Civil Engr works like washing pit carriage watering arrangement, pathway, service building, stabling lines etc. awarded.
➡️All service buildings completed.
➡️Washing pit of 585 mtr completed.
➡️4 stabling line linking completed.
➡️Electrical & OHE contract awarded.
➡️All infringement removed for phase I work.
✳️Work In Progress –
⏩Construction of New High level platforms with 2 loops of 26 coach length & covershed of 500 mtr with carriage watering arrangement.
⏩Construction of FOB connectivity to Proposed platforms.