#Admin #Moderator Source Cr X Handle
#CRInfraUpdates
Ahmednagar-Beed - Parli Vaijnath New line-
🟩CR completed 147.77 km multitracking (new line/doubling/3rd/4th line) from April 2023 till date.
🪙3886.95...
more... Crs planned by CR in this year for new lines/doubling/3rd/4th line
🪙2983.47 Crs expenditure till date
🟩Ahmednagar-Beed- Parli-Vaijnath New line-
➡️Length - 261.25 km
➡️Length commissioned - 66.18 km
➡️Remaining - 195.25 km
➡️Overall Physical progress - 78%
➡️Land acquisition - 1821.56/1806.19 Hectare (99%)
🪙 Cost - Rs. 4805.17 Cr
🪙 Expenditure till date - RS 3699.Cr
A) Completed section-
Ahmednagar to Ashti (66.18 km)
B) Near completion-
(Likely commissioning this FY)
Ashti to Eganwadi (66.12 km)
C) In progress-
Eganwadi to Parli (127.95 km)
Completed works-
➡️Earthwork- 419.235/430.43 (97.40%)
➡️Major Bridge - 49/64 (77%)
➡️Minor Bridge - 250/301(83%)
➡️ROB/RUB - 126/195 (65%)
➡️Ballast supply - 6.54/7.52 Lcm (87%)
➡️ Track linking - 118.38/285.89 km (41%)
➡️Power line crossing - 568/626 (91%)
Completion of this line will improve connectivity of Ahmednagar and Beed districts and will lead to socio-economic development of region.