TODAY RM PIYUSH GOYAL meeting with Karnataka cm at Bengaluru discuss Bengaluru suburban railway
Highlights
Speed of railway construction in Karnataka b4 2014/after 2014
1 .NL -23KMS / 67KMS
2.DL -35KMS/56KMS
3.RE...
more... -8KMS /171KMS
Capital investment increase 2.5times
Allotted Rs 400cr for suburban railway in this year budget :cm hdk
Suburban highlights in today's meeting
1.total cr 23,000cr project
2.expcepted period of completion :6yrs
3. Total suburban route:160kms ( 70kms elevated +90kms ground level )
4. Total station s : 83 stations
5.interchanging with metro station s :12 station s
6.Rs6000cr worth RLY land will be given for this project
7.No phase ways work ..continue s work till take place
8. State govt will declare& likely to give final approval on Feb 25th in state cabinet meeting ..
9.all 19 conditions put by state govt has resolved ..
10. Coaches will hv A/c