Crossing ka kaam toh sab Pura Hai.. Maine last month dekha Tha station works Bhi complete Hai sab.. Bas track linking ka kaam Jo baki Hai wahi ssbse main Hai jab tak woh nhi ho Jata kuch nhi kaha Jata.. Most probably August last ya September first week tak sab complete ho jayega including diamond crossing.. Later On CRS inspection will be there which is expected in last week of September or first week of October.. I think From November trains will be operational on ASH-STP section..Now for inauguration, State railway minister Manoj Sinha is just for his region.. He has not time inaugurate GD-BRK section.. ASH-STP will not take more time after CRS because it's a project related to Capital's as well as NR railway DEVELOPMENT..