some new trains,new lines,doubling and tripling for karnataka which is in budget.
1)Shornur-Mangalore track (tripling)
2)guntakal-Wadi track (tripling)
3)Bangalore - Hubli track(doubling) (out of which bangalore - tumkur and arsikere -chikjajur has been done)
4)yeliyur...
more... (mandya) - mysore track (doubling)
5)yelahanka - guntakal, gooty via puttaparthi, dharmuvaram (doubling)
6)bidar - gulbarga new line (out of which bidar -humnabad has been done)
7)raichur - mahbubnagar new line (only 25 km left)
8)raichur -munirabad new line (out of which munirabad-gangawati, 5 km from Raichur has been done)
9) gadag -wadi new line (2 km has been done)
10)gadag -haveri (0 km done)
11)chennai -vasco da gama doubling (out of which chennai-koppal done,hubli -gadag 10 km done)
12)chikmaglur - sakleshpur line (only 10 km done)
13)bangalore -jolarpettai track (tripling)
14)tumkur - raydurg new line
15)hubli-ankola new line (only 20km done)
16)bangalore - ramnagaram train 5 days a week
17)chennai-bangalore train daily
18)bangalore-mangalore night and day train via arsikere
19)hyderabad gulbarga intercity express via wadi jn
thanks
regards
navaneeth